Environmental Settlements: Force Majeure Claims Related to COVID-19
Force majeure in environmental settlements. Environmental force majeure provisions typically track commercial force majeure provisions, focusing on whether events beyond the control of a company may contribute or has contributed to a delay in performance. Environmental settlements can depart from the commercial world in that they often impose a litany of process hurdles for invoking force majeure.
These process hurdles include detailed early notification requirements. The settling party typically has a limited period of time (a few days) to invoke force majeure that runs not from the date of the force majeure event but often from when the settling party first knew or should have known of the likely delay. The force majeure notification often must contain significant detail and documentation regarding the causes of the delay and what could be done to minimize the delay. In turn, the enforcing agency must affirmatively agree that a delay is due to a force majeure event and determine the length of the delay it will permit. Any disagreements are typically subject to dispute resolution provisions in the settlement agreement.
Invoking force majeure for COVID-19. These hurdles become particularly problematic in the current climate of COVID-19, where delays in meeting settlement requirements might occur due to workforce reductions or other disruptions that are difficult to predict and evolving rapidly. For a typical force majeure event such as a hurricane or labor disruption, force majeure provisions, while onerous, may be manageable. But how do these procedural terms apply to a well-known contagion in its early stages, particularly where reliable methods of detection are only now emerging? These questions are of vital importance because several strategically important industries remain subject to numerous environmental settlement agreements. Petroleum refiners, for example, have 95 percent of their capacity under EPA consent decrees.
Companies should thus consider preparing if they believe there is a reasonable chance that COVID-19-related business interruption could delay performance of any obligations under any of their environmental settlements. Preparation could involve reviewing the force majeure provisions in their in-effect settlements, assessing the risk of business interruption to their settlement obligations, establishing internal communication plans to stay timely apprised of delays or escalating risks and considering plans to timely inform relevant agencies in accordance with any force majeure process requirements. Finally, record retention of all information potentially relevant to a force majeure claim may be beneficial in the event of a dispute.
Other considerations. In addition to invoking force majeure, companies must consider how they treat invocation of force majeure by other companies. For example, companies may have suppliers that are claiming force majeure against the company at the same time that the company is claiming force majeure against the government.
COVID-19-related disruptions could affect companies’ compliance with environmental obligations beyond settlements, such as day-to-day compliance with permits and other environmental regulatory requirements. Most environmental regulations do not have force majeure provisions that can be used by agencies to excuse noncompliance or extend deadlines, but nonetheless defenses such as “Act of God” can often be defense to liability. Notifying agencies of potential COVID-19-related delays in performance or noncompliance with permits and other environmental regulatory requirements may support such a defense.
Other agencies have already recognized that COVID-19 may be grounds for limited relief. On March 4, 2020, the Securities and Exchange Commission issued an order providing publicly traded companies an additional 45 days to file disclosure reports, provided certain conditions are met, such as explaining the impact the virus might have on a company. It is possible that EPA and even some state agencies may consider issuing guidance on these topics.
律师广告—Sidley Austin LLP 是一家全球性律师事务所。我们的地址及联系方式可在 www.sidley.com/en/locations/offices 查阅。
Sidley 提供本信息仅作为向客户及其他友好人士提供的服务,且仅供教育目的使用。本信息不应被解释或依赖为法律意见,亦不构成律师与客户关系。读者在未寻求专业顾问意见之前,不应依据本信息采取任何行动。Sidley 和 Sidley Austin 指 Sidley Austin LLP 及其关联合伙实体,详见 www.sidley.com/disclaimer。
© Sidley Austin LLP
联系我们
如果您对本次 Sidley 更新有任何疑问,请联系您平时合作的 Sidley 律师,或
Capabilities
Suggested News & Insights
- Stay Up To DateSubscribe to Sidley Publications
- Follow Sidley on Social MediaSocial Media Directory